SOCIAL, ENVIRONMENTAL AND CLIMATE ASSESSMENT PROCEDURES

  • Compliance with National Law

In the project implementation, IFAD required the NIA-IO to comply with the national law. As of 15 February 2021, Certificate of No Overlap for 10 CISs was issued on February 4, 2021. The water permit applications of 10 CISs are ready for submission to NWRB. Clearance on Protected Area for Lake Lanao and surrounding watersheds was issued on January 28, 2021. Pending for compliance is the Tree Cutting Permit and Chainsaw & Genset Permit which will be issued by BARMM-MENRE.

 

Required Permit/Certification under National Laws

Target

Actual

Remarks

  1. Certificate of No Overlap with the BARMM-Ministry of Indigenous Peoples Affairs (MIPA)

10 CIS

10 CIS

Certification issued on February 4, 2021

  1. NWRB- Water Permits

10 CIS

10 CIS

Application ready for processing to NWRB

  1. Protected Area clearance for Lake Lanao and surrounding watersheds

10 CIS

10 CIS

Clearance issued on January 28, 2021

  1. Tree cutting Permit from BARMM-MENRE

5 CIS

 

Not yet available, request submitted to that office

  1. Chainsaw and Genset Permit from BARMM-MENRE

5 CIS

 

Not yet available, request submitted that office 

 

  • Adoption to Climate Change

The adoption of climate change in the project targeted 4 outputs, but this will be conducted after the construction activities.

 

Target Output

Status

  1. Orientations and Trainings on Climate Change Mitigation and Adaptation and Risk Reduction Strategies

To be undertaken after construction activities

  1. Provincial Climate Change Action Plan

To be undertaken after construction activities

  1. Provincial Sanitation Plan and Monitoring of Schistosomiasis

To be undertaken after construction activities

  1. Promote Integrated Pest Management

To be undertaken after construction activities